Previous project updates

Project Status Update 10 June 2025

Construction of the Northern Suburbs Community Recreation Hub is progressing strongly, with all major building elements such as roofing, concrete works, cladding, and precast panels currently being installed.

Another important milestone has been achieved with the completion of the precast skirts; a protective feature designed to safeguard the lower sections of the building.

On the northern side of the development, there has been significant visual progress. The indoor netball courts are beginning to take shape, providing the community with a clear sense of the scale and design of the new facility.

In April 2025, planning approval was granted for signage at the site (Permit No. DA0063/2025) under section 57 of the Land Use Planning and Approvals Act 1993.

The project team remains focused on maintaining strong progress and delivering a high-quality, multi-use facility that will serve the local community for many years to come.

Project Status Update 20 December 2024

We are pleased to share the latest developments regarding soil remediation efforts at the Hub.

A separate Development Application (DA) for soil remediation was submitted to the City of Launceston on 15 November 2024.  Planning approval has been granted, and Planning Permit DA0508/2024 was issued on 13 December 2024.

As part of the project, berms will be created using the excess soil that has been heaped during the earthworks process. These berms will contribute to sustainable soil management and site improvements.

Project Status Update 20 May 2024

Following completion of an open tender process in May 2024, Tasmanian firm Vos Construction & Joinery Pty Ltd was awarded the Stage 2 Main Works Contract to deliver the construction phase of the Hub.

The design phase of the project is now complete. The final design incorporates specialised advice from the Premiers Disability Advisory Committee (PDAC) to ensure we are meeting the needs of all members of our community.  Early and ongoing consultations with PDAC identified the need for removal of any impediments or barriers. Including some notable access design elements.

  • Accessible car parking near the main entry with access to low level EV charging stations.
  • Adult Accessible Change Facility to meet the requirements of the Changing Places specification.
  • Raised pedestrian crossings in the carpark with kerb ramps to provide a continuous surface and equal access from the car park.
  • Lower bench height section at Reception for wheelchair users.
  • Six DDA compliant bathroom amenities.
  • Access to the dedicated netball courts via a ramp to provide ease of movement for all patrons.

Project Status Update 15 November 2024

On 8 November 2023, the City of Launceston (CoL) approved the Development Application and issued a Planning Permit for Stage 2 Main Works.

Infrastructure Tasmania will continue to work with key stakeholders to deliver this exciting transformative project which is expected to open to late 2025.

Project Status Update 1 March 2024

Local Tasmanian firm, Anstie Constructions Pty Ltd, have completed the Stage 1 Early Works Package. Works included demolition, site remediation, limited services and latent conditions works.